Lesson 32 Review

  1. Under the Job Properties > Schedule tab, which setting can be enabled to account for plugged costs (e.g., for subcontractors)?

    1. Resource price/unit

    2. Expense Costs

    3. Schedule ID

    4. Actuals

  2. For InEight Estimate schedule integration with Primavera, which of the following can be sent from your estimate to the schedule? (Select all that apply)

    1. Activity data

    2. Cash Flow graphs

    3. Resource data

    4. Cost data

    5. Price data

  3. The Schedule Plug Days option allows you to define the duration in the schedule separate from the duration defined for your cost items on the Production tab.

    1. True

    2. False

Lesson 32 Summary

As a result of this lesson, you can:

  • Set up scheduling options

  • Update Schedule from InEight Estimate

  • Update InEight Estimate from Schedule

  • Manage changes between estimate and schedule